Now onto the good stuff…
Note to all
- The motion light doesn’t work and the back plate leaves a gaping hole in the stucco. After working on it four times they’ve only gotten the back plate fixed.
- The double light switches for the ceiling fans/lights turn on the same fixture and don’t work on the other. This is fixed, but still odd. I’ll leave it at that.
- They cut the hole for the bathroom vent too long and left a visible hole. Their first solution was to reposition the vent (so the hole ended up on the other side). I hope they weren’t surprised when I told them their solution was unacceptable. Next they used caulk to try to hide the hole. That looked completely ridiculous. Then they cut a sliver of drywall to fill the hole but didn’t tape/float it. Finally my contractor had Lazaro fix the hole and billed it back to Bryant Electric.
- This is the best! Even better than the bathroom vent. They came back to hook up wiring for the tankless water heater (it’s gas, but needs electricity too). To do this they unplugged the dryer and plugged the water heater into the dryer’s outlet! What this means is the water heater, dryer, and washing machine cannot all work together. One has to be unplugged. Genius! To fix this they ended up installing a piggyback-type outlet, so the outlet is about six inches deep. This isn’t good because then the washer and dryer have to stick out six inches. They’re supposed to fix that today, so I can’t wait to see what they do this time.
- They installed another piggyback-type outlet at the top of the stairs. Apparently this is code, but they didn’t ask us about placement. It sticks out so far we’re worried someone going down the stairs will trip over it. Hopefully that will be fixed today. I also think this is the reason for a hairline crack in the stucco about a foot above the outlet.
- They couldn’t figure out how to install the Ikea track lights we got for the kitchen, so I had to fill multiple “mistake” holes in the ceiling.
I think that’s it. It’s quite possible I’m leaving something out. It’s a long list to keep track of. I really hope the next post has nothing to do with electrician problems.
On a more positive note I cannot tell you how much I love our ductless heating and air conditioning unit. It is the greatest thing ever! It’s so quiet I can’t tell when it’s on. I haven’t been able to truly test it since my office isn’t up there yet, but while I’ve been painting it’s been great. The guys who installed it were great too. They arrived with a giant glass carafe of coffee—the drip-coffee kind that’s in the shape of an hourglass with the leather wrap around the middle. There’s something uniquely
Another positive is that the floors are done and gorgeous. We are so lucky to have old oak floors in such great shape. I’m thankful the previous owner had covered them up with ugly black carpet squares. To fix the hole where the floor heater used to be and where the kitchen wall used to be they simply pulled up all the hardwoods on the kitchen/dining room side and mixed in a few pieces of old with new.
I don’t think I wrote about our picky tile guy, Randy. He did a great job too, but not without a wee bit of drama. He wouldn’t work while anybody else was there, so he put us behind by at least three days. I guess when you’re really good at your job you get what you want. Still, I think it was absolutely ridiculous. To clarify, Randy only did the subway tile in the shower. Brad, my hero, laid the penny tile on the floor. He doesn’t think he did a good job, but I think it looks gorgeous!
I haven't been able to get a great shot of the bathroom. I think my lens needs a cleaning because photos aren't coming out right lately. However, my wide-angle lens seems fine, so here's a better photo of the bathroom using that. Note that I haven't tackled painting the wood trim yet (and the quarter-round hasn't been installed).
A shot of my office and the bedroom (on the other side of the half-wall):

1 comment:
That is looking really nice. It's so clean. Very cool fans. Molly, you will have no excuse to get A LOT of work done with a new office like this!
Post a Comment